By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
NetZero.VN - Net Zero Viet NamNetZero.VN - Net Zero Viet NamNetZero.VN - Net Zero Viet Nam
  • English
    • Tiếng Việt
  • Home
  • News / Events
    • Events
    • Cà phê Net Zero
    • Net Zero Talks
  • Opinion
  • Projects
  • Forums
  • Topics
    • Agriculture – Forestry
    • Construction & Transport
    • Culture, Sports, Tourism
    • Education & Communication
    • Energy
    • Finance
    • Industry
    • Policies
    • Resources & Environment
    • Science & Technology
    • Sustainable Development
  • Multimedia
    • Podcast
    • Videos
    MultimediaShow More
    [HTV] Net Zero Through Heritage
    NetZero.VN 11/03/2025
    Carbon credit market: New opportunities for Vietnamese businesses
    Vietnam News Agency 29/05/2024
    Vietnam works to prevent biodiversity degradation
    Vietnam News Agency 16/04/2024
    Vietnam develops offshore hydrogen production
    Vietnam News Agency 10/03/2024
    Green energy – A trend in sustainable development
    Vietnam News Agency 07/01/2024
  • Resources
    • Legal documents
    • Presentations
    • Publications
    • Reports
Notification Show More
Font ResizerAa
NetZero.VN - Net Zero Viet NamNetZero.VN - Net Zero Viet Nam
Font ResizerAa
  • English
    • Tiếng Việt
  • Home
  • News / Events
    • Events
    • Cà phê Net Zero
    • Net Zero Talks
  • Opinion
  • Projects
  • Forums
  • Topics
    • Agriculture – Forestry
    • Construction & Transport
    • Culture, Sports, Tourism
    • Education & Communication
    • Energy
    • Finance
    • Industry
    • Policies
    • Resources & Environment
    • Science & Technology
    • Sustainable Development
  • Multimedia
    • Podcast
    • Videos
  • Resources
    • Legal documents
    • Presentations
    • Publications
    • Reports
Follow US
© 2023-2025 NetZero.VN | Net Zero VietNam JSC. All Rights Reserved.
NetZero.VN - Net Zero Viet Nam > Topics > Energy > Measures for offshore wind must be carried out rapidly
EnergyNews

Measures for offshore wind must be carried out rapidly

Vietnam’s ambition to achieve 6GW of offshore wind capacity by 2030 is increasingly adrift, with not enough work carried out on legalities and developer support.

Vietnam Investment Review 25/06/2024
SHARE
There are currently complex investment processes, leading to long preparation time and potential implementation risks

Last week at a workshop in Hanoi, Mark Hutchinson, director and chair of the Southeast Asia Taskforce at the Global Wind Energy Council (GWEC), said that Vietnam had only developed intertidal wind projects near the coast, and no real offshore wind (OSW) ventures had been started.

According to Hutchinson, an OSW scheme takes 6-8 years to set up, and thus the first potential pilot project may not be ready until 2032.

“Under the first draft pilot mechanism for OSW regulations, the GWEC and our members encouraged collaboration with experienced developers. The industry supports the move to competitive procurement for several reasons, mainly because of its transparency. A transparent, competitive procurement process will push OSW forward in Vietnam,” Hutchinson said.

The key suggestions to speed up progress mentioned at the workshop included implementing a simple remuneration mechanism for initial pilots, developing a streamlined permitting process, a robust marine spatial planning and site allocation approach, defining a clear auction timeline, and enhancing power purchase agreement bankability to engage international finance.

Bui Van Thinh, chairman of Binh Thuan Wind and Solar Power Association, said, “There is a lack of regulations, policies, spatial planning, and price policies for electricity. Electricity is increasingly lacking, but electricity projects cannot be implemented. Investors can generate electricity, but are concerned about prices.”

The cost of wind power production has decreased sharply, from about 25 US cents per kWh more than 10 years ago to about 10 US cents per kWh today, and it may decrease to 6 US cents per kWh in the future.

Nguyen Hoang Anh of Vietnam Electricity (EVN) said that building a power transmission system for OSW initiatives was difficult due to electricity regulations, and the national marine spatial master plan for this decade has not been approved.

“There is no planning for underground cable routes connecting such power projects. There are complex investment processes, leading to long preparation times and potential risks during implementation, and lack of regulations on investment in OSW projects in general. There is no clear and transparent mechanism for power prices or principles to regulate the field,” he said.

Meanwhile, an energy outlook report released by EVN and its Renewable Energy Authority, in conjunction with the Danish Energy Agency and the Danish Embassy, noted that in the net-zero scenario, OSW capacity will expand to 84GW by 2050.

Crafting the necessary framework to roll out the planned pilot schemes for OSW is therefore a prerequisite to achieve the targets stated in Power Development Plan VIII (PDP8) and beyond, considering the long planning and construction time needed, it said.

“This includes implementing adequate regulations and guidelines including marine spatial planning, a price framework, and a clear permitting process to ensure speed of implementation,” said Rasmus Munch Sørensen, advisor for the Danish Energy Partnership Programme for 2021-2025. “At the same time, it is important to conduct an analysis of grid point connections, build needed seaport infrastructure, and ensure a skilled workforce.”

Pilot projects, as outlined under the PDP8, should be progressed as soon as possible to build the necessary experience, mitigate and minimise risks and costs, and increase confidence for investors, Sørensen added.

Marine spatial planning proposals are expected to be submitted to the National Assembly before the end of June. Previously, in April, the Ministry of Industry and Trade submitted a draft proposal for the pilot mechanism of related projects, which involves an energy steering committee that was established in November 2023 to oversee related ventures.

The Asia-Pacific region is expected to add 215GW of offshore wind power generation capacity between now and 2033, and China will be responsible for three-quarters of the figure, according to the latest estimates by GWEC.

Based on the GWEC Market Intelligence data released in June, Taiwan will account for 7 per cent of the new installations, and South Korea for 5 per cent. Japan, Vietnam, and India will be responsible for 3 per cent.


Juan Frías, head, Offshore Wind Auctions and Cost Engineering, OWC

A two-stage model is proposed for Vietnam to consider a review of the legal framework. In a one-stage competition model, exclusivity over survey rights and the offtake are awarded simultaneously. This fixes the electricity tariff at a very early stage in the development process.

In Vietnam, as in other early-stage markets, there are major uncertainties around development timelines, supply chain availability, financing conditions, and costs. These pose major risks to the business cases of investors. In a competitive selection process, these issues could lead to very high-risk or delayed projects. Both situations would diminish public and political support for OSW and erode the confidence of financiers.

The key objectives of the competitive selection model proposed for Vietnam will ensure the most transparent, reasonable, and comparable auction criteria, and give confidence to investors on future opportunities. However, there is no one-size-fits-all tendering scheme for related projects, as competitive selection processes are market-specific.

Denzel Eades, managing director Pioneer International Consulting

The Vietnamese government needs to focus on quickly promoting OSW power policies, as the regulatory framework in Vietnam remains underdeveloped.

The goal to have the first projects put into commercial operation by 2030 is becoming more and more difficult. The process of developing legal regulations and legal frameworks takes a long time, on average 2-3 years, and a new law may need to be promulgated.

In addition, because many related regulations overlap between different ministries and government agencies, close coordination between relevant agencies is extremely important. With current common challenges, achieving the 2030 targets will require great effort and quick actions from the government.

In Vietnam, the investor selection process applicable to OSW has also not been clarified. Competitive tendering for large-scale power projects has been unsuccessful, and those subject to bidding require a state-issued pre-feasibility study and state-assisted land clearance. Specific requirements for the selection of investors have not been determined and the authorities responsible for investor selection are subject to review.


Nguyen Thu

TAGGED:offshore wind
SOURCES:Vietnam Investment Review
Previous Article Southeast Asia’s largest wastewater treatment facility to open in HCM City in mid-2025
Next Article Revealing the truth about the carbon credit market
Leave a review Leave a review

Leave a Review Cancel reply

You must be logged in to post a comment.

Latest
Airlines stick to net zero target despite green fuel doubts

The International Air Transport Association, which represents about 350 airlines, said hitting…

Vietnamese businesses go green: Keeping pace with technology, breaking through innovation

In the context of increasingly stringent global environmental standards, green transition is…

HCMC’s green index reveals mixed progress amidst national commitment

According to a recently released World Bank report, and reaffirming commitments made…

Logicross enters Vietnam with two modern and sustainable warehouses

What makes Logicross warehouse platform unique? As logistics demands grow more specialised,…

Proposal to build 2 renewable energy centers

On May 30, 2025, the Ministry of Industry and Trade issued Decision…

Switzerland pledges $50 million to support Vietnam’s sustainable development

The Swiss State Secretariat for Economic Affairs (SECO) will allocate a budget…

The key to paving the way for Vietnam’s renewable energy breakthrough

Completing policy mechanisms to mobilize resources for renewable energy Exchanging at the…

AFD and EVNNPT sign $75 million financing deal to enhance transmission grid

The agreement was signed by Rémy Rioux, general director of AFD, and…

Green finance criteria needed to hit net-zero goal

As green finance plays a key role in green growth, Việt Nam…

Bình Dương charts new path with green, digital and innovative industrial model

After nearly three decades leading Việt Nam’s industrial development, the southern province…

Facebook Instagram Linkedin Twitter Youtube
NETZERO.VN
  • About us
  • Our team
  • Strategic Partners
  • Contact
Infomation
  • Forums
  • Multimedia
  • Recruitment

Sign up for free

Subscribe to our newsletter

Join the community
© 2025 NetZero.VN | Net Zero VietNam JSC. All Rights Reserved.
Welcome Back!

Sign in to your account