By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
NetZero.VN - Net Zero Viet NamNetZero.VN - Net Zero Viet NamNetZero.VN - Net Zero Viet Nam
  • English
    • Tiếng Việt
  • Home
  • News / Events
    • Events
    • Cà phê Net Zero
    • Net Zero Talks
  • Opinion
  • Projects
  • Forums
  • Topics
    • Agriculture – Forestry
    • Construction & Transport
    • Culture, Sports, Tourism
    • Education & Communication
    • Energy
    • Finance
    • Industry
    • Policies
    • Resources & Environment
    • Science & Technology
    • Sustainable Development
  • Multimedia
    • Podcast
    • Videos
    MultimediaShow More
    [HTV] Net Zero Through Heritage
    NetZero.VN 11/03/2025
    Carbon credit market: New opportunities for Vietnamese businesses
    Vietnam News Agency 29/05/2024
    Vietnam works to prevent biodiversity degradation
    Vietnam News Agency 16/04/2024
    Vietnam develops offshore hydrogen production
    Vietnam News Agency 10/03/2024
    Green energy – A trend in sustainable development
    Vietnam News Agency 07/01/2024
  • Resources
    • Legal documents
    • Presentations
    • Publications
    • Reports
Notification Show More
Font ResizerAa
NetZero.VN - Net Zero Viet NamNetZero.VN - Net Zero Viet Nam
Font ResizerAa
  • English
    • Tiếng Việt
  • Home
  • News / Events
    • Events
    • Cà phê Net Zero
    • Net Zero Talks
  • Opinion
  • Projects
  • Forums
  • Topics
    • Agriculture – Forestry
    • Construction & Transport
    • Culture, Sports, Tourism
    • Education & Communication
    • Energy
    • Finance
    • Industry
    • Policies
    • Resources & Environment
    • Science & Technology
    • Sustainable Development
  • Multimedia
    • Podcast
    • Videos
  • Resources
    • Legal documents
    • Presentations
    • Publications
    • Reports
Follow US
© 2023-2025 NetZero.VN | Net Zero VietNam JSC. All Rights Reserved.
NetZero.VN - Net Zero Viet Nam > Topics > Energy > MoIT proposes delaying offshore wind power until after 2030
EnergyNewsPolicies

MoIT proposes delaying offshore wind power until after 2030

The Ministry of Industry and Trade (MoIT) has proposed delaying the development of offshore wind power until after 2030, instead of the original target of about 6,000MW in the next five years.

Vietnam Investment Review 20/02/2025
SHARE

According to Power Development Plan VIII, the country’s offshore wind (OSW) power capacity should reach 6,000MW by 2030, but no projects have thus far been approved.

At a meeting on February 19, Minister of Industry and Trade Nguyen Hong Dien said that OSW power would need serious investments.

“Adjustments to PDP VIII are expected to develop this power source after 2030, reaching about 17,000MW by 2035,” he said.

Instead of offshore, in the next five years, Vietnam will develop onshore and nearshore wind power with 27,800-34,670MW, an increase of about 15 per cent compared to the current plan.

The World Bank has assessed Vietnam’s OSW power potential at about 600GW. In terms of prospects, this energy source could provide 12 per cent of the country’s total electricity output by 2035.

Foreign investors in the renewable energy sector have introduced plans to implement OSW power projects in Vietnam, such as CIP Group (Denmark) and PNE (Germany). Two years ago, 36 domestic investors applied to research OSW power, but the Ministry of Natural Resources and Environment halted licences due to legal issues.

The development of OSW power projects faces major difficulties, such as inconsistent legal regulations on managing sea activities, large investments, and issues related to national defence and security.

Chairman of the European Chamber of Commerce in Vietnam Bruno Jaspaert said that an OSW power project takes at least three years to build. If these projects were to go into operation by 2030, construction needs to start in 2027, and all licences must be ready a year before.

The government has set a GDP growth target of at least 8 per cent this year, and double digits for the 2026-2030 period. To produce enough power to achieve this target, domestic demand by 2030 will be around 183,300-236,360MW, an increase of 18-54 per cent compared to the current plan, according to the MoIT.

The total capacity of coal-fired thermal power by 2030 will increase by 928MW compared to PDP 8, while thermal power using domestic gas sources is expected to reach about 10,861MW, unchanged from the current plan.

The total capacity of liquefied natural gas in the next five years is forecast at 8,824MW, a decrease of about 13,576MW compared to the target set in PDP 8, while hydropower, renewable energy, and battery storage sources will soar.

Concentrated and rooftop solar power will also increase by 25,867-52,825MW to 46,459-73,416MW. This source can be deployed quickly to meet demand in the 2026-2027 period.

The total capacity of the two nuclear power plants that have just started construction in Ninh Thuan province, is expected to be about 6,000-6,400MW, completed in 2030 and put into operation in the 2030-2035 period. Then by 2050, about 4,500-5,000MW of nuclear power will be added in the north and about 3,000MW in the central region.

Minister Dien said that the total investment for 2026-2030 has been estimated at $136-172 billion, including $118-148 billion for electricity sources, and $18-24 billion for the transmission grid.

To meet the large capital demand, the MoIT proposed solutions to diversify capital sources and forms of mobilisation (like bank credit, aid, and the stock market), along with domestic and foreign resources.

Nguyen Huong

TAGGED:offshore wind powerPDP 8
SOURCES:Vietnam Investment Review
Previous Article Vietnam’s carbon market pilot from policy to profit
Next Article Reasonable electricity prices to attract investment in Việt Nam’s energy sector
Leave a review Leave a review

Leave a Review Cancel reply

You must be logged in to post a comment.

Latest
Proposal to build 2 renewable energy centers

On May 30, 2025, the Ministry of Industry and Trade issued Decision…

Switzerland pledges $50 million to support Vietnam’s sustainable development

The Swiss State Secretariat for Economic Affairs (SECO) will allocate a budget…

The key to paving the way for Vietnam’s renewable energy breakthrough

Completing policy mechanisms to mobilize resources for renewable energy Exchanging at the…

AFD and EVNNPT sign $75 million financing deal to enhance transmission grid

The agreement was signed by Rémy Rioux, general director of AFD, and…

Green finance criteria needed to hit net-zero goal

As green finance plays a key role in green growth, Việt Nam…

Bình Dương charts new path with green, digital and innovative industrial model

After nearly three decades leading Việt Nam’s industrial development, the southern province…

Reliable power policy urged for business progress

Nguyen Van Dat, deputy director of Thai Nguyen Zinc Electrolysis Plant, pointed…

Deputy PM sounds alarm on worsening urban pollution

Deputy Prime Minister Trần Hồng Hà has urged ministries, sectors and local…

How to make motorcycle emission controls effective

Controlling emissions from motorbikes is one of the main measures which can…

Enterprises seek cost-cutting solutions amid electricity hikes

Vietnam Electricity (EVN) implemented a 4.8 per cent increase in the average…

Xem thêm

EnergyNewsPolicies

Offshore wind development plans receive new lease of life

Vietnam Investment Review 24/03/2025
EnergyNews

PM pushes for offshore wind power pilot project in 2025

The Saigon Times 05/01/2025
EnergyNews

Clean electricity export: a bumpy road ahead

Vietnam News Agency 25/08/2024
EnergyNewsPolicies

Trade ministry proposes State-owned groups to pilot offshore wind power development

NetZero.VN 25/07/2024
Facebook Instagram Linkedin Twitter Youtube
NETZERO.VN
  • About us
  • Our team
  • Strategic Partners
  • Contact
Infomation
  • Forums
  • Multimedia
  • Recruitment

Sign up for free

Subscribe to our newsletter

Join the community
© 2025 NetZero.VN | Net Zero VietNam JSC. All Rights Reserved.
Welcome Back!

Sign in to your account